摘要: The US Federal Energy Regulatory Commission (FERC) has changed its world. On 20 December 1999, it issued Order 2000, final rule on regional transmission organizations (RTOs). 25 February followed this with 2000-A, which responded to requests for rehearing from many parties "We meant what we said", and also clarified a few fine points. 2000 calls for, but does not quite require, companies owning systems put the grid under control of RTOs. FERC requires transmission-owning jurisdiction file certain papers by late or early 2001. These can be either proposals form RTOs progress reports development RTO proposals. will have sole responsibility operation expansion system, maintaining short-term reliability, establishing managing tariffs, responding service.