作者: Lei Gan , Gengyin Li , Jeremy Lin , Ming Zhou
DOI: 10.1016/J.IJEPES.2017.01.020
关键词:
摘要: Abstract With the growing development of intermittent renewable energy sources, such as wind and solar, transmission planners are faced with uncertainly varying generations resultant probabilistic power flow. A bi-level programming model is proposed to coordinate process decision making reliability assessment. Based on concept life cycle cost (LCC), its minimization can be defined objective function a planner. This upper level problem needs solved jointly lower optimal flow minimizing load shedding in system. Hence transformed into Mathematical Programming Equilibrium Constraints (MPEC) Karush-Kuhn-Tucker conditions. Due nonlinearity nature MPEC, disjunctive inequalities Generalized Benders Decomposition methods used solve this problem. Results both Garver’s 6-bus test system realistic 63-bus illustrate rationality validity method.