作者: Xinwei Shen , Qiuwei Wu , Hongcai Zhang , Liming Wang
DOI:
关键词:
摘要: We propose a planning method for offshore wind farm electrical collector system (OWF-ECS) with double-sided ring topology meeting the “N-1” criterion on cable faults, in which the submarine cables layout of OWF is optimized considering cable length and power losses. The proposed mixed-integer quadratic programming (MIQP) model is based on the Capacitated Vehicle Routing Problem (CVRP) formulation and power network expansion planning, which could approximate the power losses in OWF-ECS. In addition, cross-avoidance constraints are proposed to avoid crossing cables, and the minimum k-degree center tree model is included to improve the convergence. Case studies on OWFs with 30 and 62 WTs demonstrate the effectiveness of the proposed method. Considering the potential outage cost in the radial topology, the total cost of the planning result is reduced by up to 25.9% with reliability …