Avoidable Transmission Cost is a Substantial Benefit of Solar PV

作者: Edward Kahn

DOI: 10.1016/J.TEJ.2008.05.012

关键词:

摘要: The cost burden of new large-scale transmission projects is exacerbated when low-capacity-factor generation, such as wind and solar, requires dedicated lines. Solar PV at sufficiently large scale avoids expensive incremental because it can be located the load center.

参考文章(6)
Severin Borenstein, The Market Value and Cost of Solar Photovoltaic Electricity Production University of California Energy Institute. ,(2008)
James B. Bushnell, Steven E. Stoft, Improving private incentives for electric grid investment Resource and Energy Economics. ,vol. 19, pp. 85- 108 ,(1997) , 10.1016/S0928-7655(97)00003-1