Predicting downtime costs of tracked hydraulic excavators operating in the UK opencast mining industry

作者: David J. Edwards , Gary D. Holt , Frank C. Harris

DOI: 10.1080/01446190210163552

关键词:

摘要: This paper describes the development of a model to predict hourly cost downtime (using regression equations) for tracked hydraulic excavators operating in UK opencast mining industry. A three-stage process was utilized model's development. The first stage predicted machine cycle times, second hire costs per hour and third used outputs two forecast breakdown. Both time models were revealed be good predictors, as exhibited by ‘high’ R2 values 0.86 0.95, respectively. plant expert employed within Defence Logistics Organisation, Ministry Defence, validated these which predicted. Future research work will aim enhance predictive ability developed, expand cover other types, reproduce findings graphical tabular format improve interpretation information generated.

参考文章(8)
Robert J. Pavur, Alan H. Kvanli, Carl Steven Guynes, Introduction to business statistics: A computer integrated approach ,(1989)
DAVID J. EDWARDS, GARY D. HOLT, ESTIVATE: a model for calculating excavator productivity and output costs Engineering, Construction and Architectural Management. ,vol. 7, pp. 52- 62 ,(2000) , 10.1108/EB021132
David J. Edwards, Gary D. Holt, F.C. Harris, Predictive maintenance techniques and their relevance to construction plant Journal of Quality in Maintenance Engineering. ,vol. 4, pp. 25- 37 ,(1998) , 10.1108/13552519810369057
David J. Edwards, Gary D. Holt, Frank C. Harris, A model for predicting plant maintenance costs Construction Management and Economics. ,vol. 18, pp. 65- 75 ,(2000) , 10.1080/014461900370960
Christopher Chatfield, Alexander J. Collins, Introduction to multivariate analysis ,(1980)
D. H. Hildebrand, R. L. Ott, Statistical Thinking for Managers. Biometrics. ,vol. 54, pp. 1205- ,(1998) , 10.2307/2533885