Reducing risk in long deep tunnels by using TBM and drill-and-blast methods in the same project–the hybrid solution

作者: Nick Barton

DOI: 10.3724/SP.J.1235.2012.00115

关键词:

摘要: … drill-and-blast tunnels, but here the damage zone is actually a favourable aspect, removing the highest stresses … , when very high stresses apply, such as in-situ (principal) stresses as …

参考文章(4)
R.J. Robbins, The Application Of Tunnel Boring Machines To Bad Rock Conditions ISRM International Symposium. ,(1982)
N. Barton, E. Grimstad, The Q-system following twenty years of application in NMT support selection International Journal of Rock Mechanics and Mining Sciences & Geomechanics Abstracts. ,vol. 5, ,(1995)
S. Mitani, H. Iwai Isahai, T. Iwai Mendes, Relations Between Conditions of Rock Mass And TBM's Feasibility 6th ISRM Congress. ,(1987)