Operations modeling and analysis of open pit copper mining using GPS tracking data

作者: Undram Chinbat , Kanna Miwa , Yifei Tan , Soemon Takakuwa

DOI: 10.5555/2429759.2429915

关键词:

摘要: Open pit copper mining plants usually comprise two major components, the open operation and ore enrichment plant. An mine is an excavation or graze made into surface of ground for purpose extracting ore. A series data obtained by a transportation control system with GPS (Global Positioning System) technology utilized to perform simulation. Operations in are based on plan must be optimized because costs expensive. In this paper, procedures proposed obtain number trucks estimate maximum capacity at pit. Then, creation truck dispatching table meeting demonstrated performing

参考文章(23)
Deborah A. Sadowski, Randall P. Sadowski, David W. Kelton, Simulation with Arena ,(1998)
R. Navon, Y. Shpatnitsky, A model for automated monitoring of road construction Construction Management and Economics. ,vol. 23, pp. 941- 951 ,(2005) , 10.1080/01446190500183917
L. K. Nenonen, A. W. Chan, P. W.U. Graefe, Interactive computer modelling of truck/shovel operations in an open-pit mine winter simulation conference. pp. 133- 139 ,(1981) , 10.5555/800072.808798
Undram Chinbat, Soemon Takakuwa, Using operation process simulation for a six sigma project of mining and iron production factory winter simulation conference. pp. 2431- 2438 ,(2008) , 10.5555/1516744.1517170
William E. Biles, Jerry K. Bilbrey, Daniel Sasso, Integration of simulation and geographic information systems: modeling traffic flow in inland waterways winter simulation conference. ,vol. 2, pp. 1392- 1398 ,(2004) , 10.5555/1161734.1161991
Robert E. Shannon, Introduction to the art and science of simulation winter simulation conference. ,vol. 1, pp. 7- 14 ,(1998) , 10.5555/293172.293175
Fernando Ramos, Lingguang Song, Katie Arnold, A framework for real-time simulation of heavy construction operations winter simulation conference. pp. 2387- 2395 ,(2008) , 10.5555/1516744.1517163
Undram Chinbat, Soemon Takakuwa, Using simulation analysis for mining project risk management winter simulation conference. pp. 2612- 2623 ,(2009) , 10.5555/1995456.1995811
Natashia Boland, Irina Dumitrescu, Gary Froyland, Ambros M. Gleixner, LP-based disaggregation approaches to solving the open pit mining production scheduling problem with block processing selectivity Computers & Operations Research. ,vol. 36, pp. 1064- 1089 ,(2009) , 10.1016/J.COR.2007.12.006